Quaker Meeting House

| Capacity | 3.76 kWp |
| Predicted Output | 3,269 kWh |
| Panel Type | REC 235Wp |
| Inverter | SMA Sunnyboy |
| Roof Type | Artificial Slate |
| Location | Woodhouse, Leeds |
Installed in August 2011 on the Quaker meeting house opposite Leeds University, with black framed panels chosen to minimise the visual impact against the black slates. Independent analysis of the system's performance by a Leeds University student indicated that this system has led to a 50% reduction in energy bills within the building.